on 02-29-2016 11:15 AM
Hello Friends,
I have started working on SAP PO.
In NWDS(ESR) I completed the configuration, I am stuck with creating a process in Process Development.
I have attached the screen shot to show the difference.
Please Help!
Regards,
Prerna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prema,
When you create the new development component make sure you select Process Composer as component type like below.
Praveen.
Hello Praveen,
I did exactly the same way,but don't understand what the actual problem is.
Hello Prerna,
Have you connected your NWDS with your PO system? I mean by providing the details of PO server?
Nitin
Make sure your PI version and NWDS match. Example if your PI version is PI 7.31 SP14 and you must use NWDS version 7.31 SP14.
Hello prena.
Your view is the problem.
at the bottom of projects you have option to change the view.select project explorer view.
Thank You so much for your help Raghuraman.
Its working now.
Glad to hear.
Please close the thread .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.