Hello Experts
While creating Shipment cost document when I select the transfer option for the shipment cost item system picks the same Purchase order.
I have a requirement to always create a new Purchase order instead of picking the open PO. Could you please suggest what settings would be require to achieve this. I look forward to your valuable inputs.
Regards,
J K Tharwani
According to the help documentation you always have to have a PO created before you can get a service entry from freight cost settlement. Shipment Cost Settlement with Service Agent - Transportation (LE-TRA) - SAP Library - see the section "Purchase order determination"
Did you read somewhere else that you can auto create POs from freight cost settlement?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your inputs Jurgen
Yes you rightly said that during freight cost settlement PO is created, and I believe the same is initiated while we select the "transfer" check box for the cost item. At this very moment the PO is created for the cost item.
I have a requirement wherein when I am working with another shipment cost document and at the time of "transfer" a new PO (same Purchase org, vendor & plant) should be created instead of system proposing the same PO.
Looking forward to your valuable inputs.
Regards,
J K Tharwani
I am not sure if you can make your desire happen.
There is an OSS note (bug fix) that removed this creation of new purchase orders: 740295 - RV54POCR: Transfer creates new purchase order in each case