on 02-18-2016 9:35 AM
Dear Experts
In standard sap system Cenvat clearing a/c will credit in excise invoice and debits at the time of MIRO entry then both will get nullify, but business want Cenvat clearing gl a/c debit with inventory itself. can some one suggest how can we achieve this?
ex: standard SAP system works as flows:
MIGO : Inventory gl a/c DR 100
GR/IR Clearing a/c CR 100
J1IEX : Cenvat BED , SED AED DR 12.50
Cenvat Clearing gl a/c CR 12.50
MIRO : GR/IR Clearing gl a/c DR 100
Cenvat Clearing gl a/c DR 12.50
Vendor a/c CR 112.50
Business requires it to be :
MIGO : Inventory gl a/c DR 100
Cenvat Clearing gl a/c DR 12.50
GR/IR Clearing gl a/c CR 112.50
J1IEX : Cenvat BED.AED,SED DR 12.50
Cenvat Clearing gl a/c CR 12.50
MIRO : GR/IR Clearing gl a/c 112.50
Vendor gl a/c 112.50
Please suggest.
Regards
Ram
Hi Rama,
This is something which is out of Box and you will have to use PnC to achieve what i m trying to explain.
Ideally this Situation is not Possible.
Regards
Rakesh Goenka
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Is it for import purchase order?
Regards,
pardhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rama,
It is through the Condition's Type's that the Clearing Account gets picked Up during MIGO and the Value to be Captured in GR IR Clearing Account.
What Business Requires is that in BSX and WRX , you will have to maintain Cenvat GL besides GR IR Clearing GL so that Certain Value of GR/IR gets Posted to Cenvat Clearing GL.
Try to get it done through FI-MM Integration.
Ideally we first Capture Excise During MIGO and then Post Excise by J1IEX Posting. But Since Business Require you to have a Split Value for GR/IR Clearing Account During MIGO then you will have to do it through FI-MM Integration.
Assign Points and Close the Thread if the Answer is Useful.
Regards
Rakesh Goenka
This is no where possible in the Standard SAP. You can only split WRX if you require during GRN. I dont see any other option.
In Pricing concept, what ever condition type you use in Pricing procedure will be added to Material cost and can be posted to separate GL account provided if the Pricing condition type's Condition category a Delivery costs.