I need to upgrade to a PPM 5.0 to PPM 6.1 on abap system NW.7.0 EHP2.
This system is connected to the SRM 7.0 EHP2 backend and Enterprise Portal 730.
If you do the upgrade of the PPM i must also provide for the upgrade on the SRM o EP?
Thank you
Hello
Sandro
Hi Sandro,
upgrade from PPM 5.0 to PPM 6.1 also requires upgrade of NW 7.02 to NW 7.4 (as PPM 6.1 requires NW 7.4 as prerequiste).
Enterprise Portal: You can continue to use the EP 7.30 also with PPM 6.1.
If the SRM is on a seperate system/instance you can also continue to use it with PPM 6.1.
If the SRM is on teh same system/instance as PPM, you need to check which SRM version
runs on NW 7.4.
Kind regards,
Florian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.