on 02-16-2016 12:26 PM
Hi All,
Inbound Delivery was reversed in VL09 and HU's were deleted instead of deassigning and then user deleted inbound delivery.
I checked VEKP table and found that VPOBJ field status is 03 and VPOBJKEY is inbound delivery#, so d-link or decoupling didn't HU didnt move to outbound delivery.
Issue - User is unable to reverse outbound delivery and HU's are not found in outbound delivery.
Error - There is no material document that can be cancelled in these HUs' history in VL09 screen.
How to change VPOBJ field status is 01 and VPOBJKEY to outbound delivery#?
Should I take ABAPer help to change the status and after that HU's will move to outbound delivery or not?
Regards
Irfan A B
Hi All,
Please update on this issue.
Regards
Irfan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Irfan,
In this case, you need to make the changes at the table level in VEKP to reverse the outbound delivery and resolve this inconsistency.
If you need help from SAP, then please raise an incident and it would be nice if you can provide us a reproducible example to find the rootcause where it should be possible for us to delete the inbound delivery when HU is linked to it.
Thanks,
Balaji
Hi Balaji,
I tried manipulating VEKP table by changing HU status from 0060 to 0040, VPOBJ - from 03 to 01, and VPOBJ OBJECT from inbound delivery to outbound delivery.
And still couldn't reverse outbound delivery in VL09 - I am getting error " Handling units have been changed. No cancellation possible.
Let me know if there is existing OSS notes or i should raise a new OSS.
Regards
Irfan A B
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.