requirement data flowing from DP to SNP and to MRP is not accurate

Former Member
0 Kudos

Whenever a forecast is created from a depot it does not hit the plant so therefore SNP will not be planned accurately and if SNP is not planned accurately they requirements flowing to MRP will definitely be wrong. How do I correct this issue.

Accepted Solutions (0)

Answers (2)

Answers (2)

marianoc
Active Contributor
0 Kudos

Hello,

Do you release the forecast from DP to SNP? Do you see the forecast in the right location in SNP?

If yes, then check the t-lane.

If not, you will need to investigate what is the problem.. Maybe the forecast is not being reléase to SNP.. check you variant in MC90 or the job settings.

Kind Regards,

Mariano

RahulHanda
Active Contributor
0 Kudos

Hello,

Could you share screen shots with an example for one product in depot and in plant? Though cross-check T-Lane between both i.e. depot & plant whether its active or not.

Regards

Rahul

Former Member
0 Kudos

Hi Rahul.

Thanks for the quick response. So what is the code to check if the T-Lane is active or not.