on 02-15-2016 8:53 AM
Hi All,
I have scenario that I have created settlement on activity level so my requirement is that after doing settlement on activity level, is my Network, WBS, Project automatically settled based on settlement on activity level or I have to settle individually after activity settlement.
Regards,
Faizan Khalil
Hi All,
can anyone tell me the solution of my query?
Regards,
Faizan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Faizan,
Automatic settlement is like, you need to create a batch job for CJB1 transaction.
First thing, from where it is getting settled to Activity ?
Once the actual cost are posted to the activity
1. Activity cost is settled to the Network
2. Network cost is settled to WBS
3. WBS cost is settled to Project
You can create batch job in SM36 with 3 different steps and schedule when it has to execute daily or monthly etc.
Regards
Terence
Hi Faiza,
We need to understand, PS project are only cost carrying object. cost on project (can be NWA, NH, WBS) needs to be settled finally to settlement object like profit center, cost center, settlement cost element and so on. This settlement allows FI and CO to extract report and draw PL balance sheet not only at project level also at enterprise structure level like company code. profit center and so on.
Hence there is need for settling the cost to final settling object.
Regards,
Pradeep
Lets make it very clear for you to understand that at activity level we procure materials and at period end the total cost of activity is settled to AUC (Asset under construction). So after our settlement of activity to AUC should I need to settle it further over network then WBS and finally to project of settlement of activity to AUC is enough?
Hi Faizan,
Below is the structure.
Project
WBS Element (AuC / FXA)
Network
Activities
1. Cost which is posted at activity level, should be settled to network
2. From Network it should to be settled to its WBS element.
If WBS element has cost, then it will be settled to AuC.
3. In the WBS element, you have AuC, so when you settle the WBS element it will go to AuC.
4. In that WBS, they will maintain Fixed Asset (FXA), from AuC the cost is settled to FXA
Additionally refer below link
Project Settlement - Costs - SAP Library
Regards
Terence
Hello,
CJB1 and CJB2 check these t-code for automatically settlement rule.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjeev,
my requirement is that once I define settlement rule and settled that activity during execution of CJ20N, from that settlement, it will automatically drive to network, WBS and project level instead of executing settlement on manually on network, WBS and project level.
I hope now you understand my question.
Regards,
Faizan
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.