Hi,
I'm working on PS BOM for one of the requirement. Steps that are carried are as below and we are facing problem when confirming finished header material into project stock along with consuming component.
Steps:
According to few earlier thread I came to know that after confirmation of activity auto GR happens for main material BOM main and also it consumes other components resulting stock of BOM main.
But on confirming the activity no auto GR not consumption of component is happening for me.
I'm I missing setting /configuration? please let me know
Regards,
Pradeep
Hi,
In Control key settings kind enable the checkboc for automatic goods movement.
Thanks
kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kishore,
Are you addressing to control key configuration t-code OP00? in PS control key within network has not got option that you have said.
How does the control key OP00 plays a role in PS?
I had used control key said by you in CN33, but after the transfer all control are in PS right?
looking forward for you inputs.
Pradeep
Thanks Kishore for input.
After doing the changes said by you can carrying confirmation on network, I could notice the requirement for material in MD04 is not visible (assumed to material requirement is fulfilled), but I'm not find material in stock of project.
Any idea of how to have the material in project stock after Auto GRN happened?
Regards,
Pradeep