I have assigned budget in 2015 to a WBS element which was not used. now business requires to revoke the budget and put that amount into a new WBS element from 2016 budget.
Please help me to find out the solution.
Regards,
Farzana
Hi Farzana,
Use tcode cj34.
Thanking you
Vengaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Farzana,
For such functionalities, SAP has provided TC CJCO which will carry forward balance budget.
Follow the link for details.
http://help.sap.com/saphelp_470/helpdata/en/02/daaa374bd81320e10000009b38f8cf/content.htm