New Commitment Value Types in Financial Planning View

Former Member
0 Kudos

Hi,

We are able to update the commitments from the WBS level to PPM Project Financial view with Value type as 40 . Now the PR/PO which are created with reference to WBS are also flowing as commitment value type 40 as total . Now we want to display the PR /PO as separate commitment items .

We have created new Value types 91 and 92 , but what is the other things to do , so that these commitments are flowed to PPM from the ECC .

Regards

Vikranth

Accepted Solutions (0)

Answers (1)

Answers (1)

priyatham_kasu2
Active Participant
0 Kudos

Hi Vikranth,

Refer to the BADI mentioned in following SCN post

Best Regards,

Priyatham