Hi,

When making any changes to the PDS in ERP (say BOM) that is using ECN, then this is creating a new PDS in APO which means the PDS in APO is doubled.

Can any one suggest about changing PDS with ECN, is this by standard?

REgards

Gomathi

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

If do the any changes in BOM with respective to change number it will transfer the changes to same PDS with different validity.

Refer consulting note 1825831 - Explanation for PDS when using the change management

Best Regards,