on 02-02-2016 8:07 PM
Hi Gurus,
I have a requirement in Feb 20th and have my planning time fence is April 14th .
We had created manually receipt element created in May 10th. When i run Planning run a new receipt element is created on April 14th.
Can any one please suggest how i can i stop system to create new receipt element on April14th and ask the system to look forward to May 10th ?
It will be really helpful if any one can suggest.
Thanks a lot
Regards,
Rajesh
Are you using SNP heuristic? You can't stop system from creating additional receipt.
In PPDS and CTM you can set maximum lateness of receipt in Product master- Demand Tab.