Account Assignment P - Stock getting consumed in GR, no inventory

former_member249044
Discoverer
0 Kudos

i have a requirement where i will give the project details in the sales order and through sales order PR and PO will create.

If the budget is exceeded then in PO it should give Error ( Upto here i had done the changes with account assignment P in PO)

But because of account assignment P the stock is getting consumed after doing the GR but not coming into the inventory.

Here i need to get the stock into sales order stock (E).

can you please help me how to get this done.

Thank you,

Shankar

Message was edited by: Jyoti Prakash

Please use precise and effective subject title to represent your discussion.

Accepted Solutions (0)

Answers (1)

Answers (1)

jpfriends079
Active Contributor
0 Kudos

Hi Shankar,

Check the config of schedule line category getting determined in the sales order. Then can you let us know the values mention in

- Item Category

- Acct Assgt Cat.

I assume your Acct Assgt Cat. maintained there is P - Project.

Thanks, JP

former_member249044
Discoverer
0 Kudos

Hi JP,

  Yes in Schedule line i had given P as Acct Assgt Cat as it should check

the budget in PO which is getting created thorugh Sales order.

  Item Category is Standard

Regards,

Shankar

jpfriends079
Active Contributor
0 Kudos

Hi Shankar,

Can you let me know the std sch line cat and requirement type getting determined?

What is movement type involved for GR?

Thanks, JP

former_member249044
Discoverer
0 Kudos

Schedule line which was created in New one where the movement type is 601 and req type also new one where the special sotck maintained as E.

the movement type in the GR is taking as 101

jpfriends079
Active Contributor
0 Kudos

Hi Shankar,

Please provide screenshot of Sch line cat and requirement type.

Thanks, JP