on 01-31-2016 4:54 PM
Hi SAP Gurus,
In our curret project,when user take a PPDS heuristic run the planned orders created are of extra quantity,which in turn the user have to create
manual orders to adjust the quantity.
Any clue what would be the issue ,we checked PP planning procedure and other settings even BOM is correct.
Your help will be appreciated
Thanks
Yash
Hi Yash,
Is the heuristic creating real surplus (Available Quantity > 0 at the last entry in the Elements tab) or only creating orders earlier than required?
2010195 Avoid surplus receipts in PPDS planning by setting Alert Threshold in product m
Apart from this, check lot-size settings, as recommended by Vikash and Marius above.
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check your lot size strategy (in the material master, tab lot size). Try with lot for lot option!
Thanks,
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check lot size parameters.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.