Dear Experts,
Greetings for the day!!!!
I have the following scenario, how we can map that one in SAP PS module.
One plant develop the Sample Products within the developing process if any particular activities are required then it is sent a request to the another plant along with the base material (example Fabric) and request received plant will complete the work by consuming the required materials ,if additional material required also it will procure it.
In this process we don't want to make the more complex of the system. Even we are not having the production order process and as well every day 100's of samples will be processing. And company using the individual plant wise profit and loss statement reports as part of costing purpose.
We tried to give the service PO to the other plant as a vendor creation, but here expenses are captured and as well while confirming the services against the service po one more time Financial documents will be generated. How we can overcome this issue.
Is there any alternate method is there.
Regards
PSJ
Hi,
this is very big subject to explain so you have to search on Help.sap.com.
also explore subcontracting with project systems.
thanks
sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
PS structures seems like a perfect fit for the process you describe. Explore HELP.SAP.COM and search for Project System.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.