on 01-29-2016 6:00 PM
Hi everybody. Recently this problem has been happening on deliveries from plant transfer POs. When the TO is confirmed for the delivery, the packing material from the UC is placed as a line item in the delivery. This is not supposed to happen, packing materials are not supposed to be copied into the deliveries in our processes. Can anyone help?
using the search term "generate delivery item" has this wiki in the hit list among the first 5 hits:
Generation of Delivery Items for Packaging Materials - ERP SCM - SCN Wiki
Knowing how they can be created should enable you to reverse the setting, check the change history of the customizing, if it worked before as desired then somebody must have changed it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks guys, I'll look into those and see if I can find out whats wrong.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi -
Can you check note number 1452388 - Packing in a Delivery Creates a New Line item.
http://service.sap.com/sap/support/notes/1452388
I recently had the same issue, and found that we had the second piece of the config in the note turned on...removing the entry removed the lines...I hope this helps.
Jim
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.