on 01-28-2016 4:44 AM
Dear All,
My requirement is to assign responsible person for particular activity in project. pl. let me know the process steps with Tcodes.
Thank you.
swapnil
You can use standard PS Workforce Planning.
Requirements are generated from an Internal Network Activity. The resources that can be assigned to the NWA are determined through the Work Center and it's connection to HR.
Use the Work force planning transactions to assign the personnel to the PS object.
Use Help.SAP.com for more detailed information.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.