on 01-28-2016 5:02 AM
i have a problem while transferring data from r/3 to apo
the pur.reques that i am creating r not moving out to apo..
Hello,
Is there an active integration model in the R/3 system, which includes the respective material and plant?
Check the queue in the APO system by calling Transaction SMQ2 in your APO system. If the queue remains displayed, restart the queue.
During the transfer of purchase requisitions, errors frequently occur due to incompletely maintained master data in R/3.
Check application log in SLG1.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Arul
Check your CPP May be your Purchase Requistion have got stucked due to missing any data . Also check inbound and out bound queues in ECC and SCM
If your issue at got resolved close these thread
Regards
Virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.