"Error during scheduling" when run the resheduling job

Former Member
0 Kudos

Hi All,

Can you please suggest for the below

when running the rescheduling job with finite strategy profile ,getting error as below and please find the attachment ,before it was running fine,

i am able to do in planning board

Error during scheduling and

terminated on 27.01.2016 at 05:11:28 o'clock

Regards

vijaya

Accepted Solutions (1)

Accepted Solutions (1)

konkasreenivasulu
Participant
0 Kudos

Hi Vijaya,

  • Change the working times and capacities of the resources.
  • Set the planning mode "infinite planning" in the strategy profile.
  • Activate the planning direction forwards or backwards and reverse in the strategy profile.
  • Change the characteristics that you have assigned to the resource.

It is better to use strategy settings deallocate instead of terminate in case of error to avoid job failure.


check whether you have used consider maximum interval in your strategy parameter for dependent objects  , please remove it .It'll work fine...


The function "Reschedule" follows an all-or-nothing logic, which means that either all selected activities on a resource can be re-scheduled or the function (better the liveCache) cancels and no activities will be re-scheduled.

One reason might be that you have a pegging relation to a fixed activity (this might be a sales order, forecast, an activity outside the propagation range...) which cannot be considered during the
scheduling. The liveCache cannot break the pegging, therefore it cancels the scheduling.

Please have a look at the note 510669 which offers a heuristic on the basis of the algorithm /SAPAPO/HEUR_PLAN_SEQ_PACKAGES. This heuristic should solve your problem. It will re-schedule as many activities as possible and will not cancel if one fails.

Depending on your current release there could be also some correction notes like

1272960

1027194

I hope It could help you

Regards,

Sreeni

Message was edited by: KONKA SREENIVASULU

Former Member
0 Kudos

Hi sreeni/All,

Before same strategy profile it was working with same setting and it is working now in test system but production it is not working,it was there as deallocate and break pegging relation and it was backward then reverse,Please suguest if anything miss if working before not now with the same strategy profile

Answers (0)