Budget AVAC not activated on WBS

0 Kudos

Hi Experts,

Budget AVAC is not executing in cj20n.

Even though I have manitained '1' in budget profile , AVAC activation while giving budget.

On wbs BUDG is coming but AVAC is not coming.

I have already eplored existing thread but could not locate this issue amongst them.

Please suggest where I have missed you.

regards

Rohit

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi All,

yes, I have  mantained the tolerance profile.

Have also run CJbv, cjbw as well.

Regards

'Rohit

mandar_mahuli
Participant
0 Kudos

have you maintained budget and released it? pls try to release  the budget from CJ32 and try.

also try by activating release checkbox in budget profile.

Former Member
0 Kudos

Hi Rohit,

Based on your setting in budget profile, no need to tick/activate the release checkbox (if it is not part of your business process) and no need to release in CJ32.

Just ensure that you have posted budget (tcode CJ30) for the project you are using.

You cannot have AVAC if BUDG is not yet active in at least 1 of the WBS elements of the project (and when you post budget, AVAC will automatically be activated).

If you like to have AVAC status even if budget has not been posted, you can activate sap note 599813 and have AVAC with tcode CJBN.

If that is not your error/problem, try checking

  1: if you have user status which prohibits activation of avac

  2. ensure that the project you have is using the budget profile

  3.  revert, and we can check other possible issues...

Regards,

Former Member
0 Kudos

Also, in your setting for tolerance limit, no need for the 2 lines with Tr Group "06" since this is already covered by the "++" setting..

Answers (4)

Answers (4)

0 Kudos

Thanks Gurus,

I have posted the Budget in cj30 before posting the ticket.

We need to have control at CRTD status. I deactivated the AVAC and again activated, now its working.

Thanks all for their input, it was helpful.

We can close the ticket.

Regards

Rohit

MTerence
Active Contributor
0 Kudos

Hi Rohit,

Thanks for your info.

Please mark the thread as answered.

Regards

Terence

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Rohit,

Have you maintained any Tolerance limits?

Regards,

Paulo

Former Member
0 Kudos

Hi Rohit,

did you maintain the Tolerance Limits for the Controlling Area-Budget Profile?

regards,

Alex

MTerence
Active Contributor
0 Kudos

Hi Rohit,

Is there any Budget allocated ?

Regards

Terence