Dear Guru,
Is it possible to set the the valuation per Purchase Requisition as "PO Price - Adopt as Gross Price" for the purchase requisitions being generated in Project System? i know how to set it up in the MM side but it seems that it is not being adopted to PR from PS.
Already made some research but can find any relevant to Project System.
Please enlighten me about this feature.
Thank you very much.
There is no configuration in PS around converting a PR to a PO. That is all in MM.
Look at OPTT for the PR Type being created by PS. Then check you MM config for that PR Type.
You can also use Info Records to set the price on a Network Activity.