Hi Gurus,

I am using /sapapo/lcout for sending Deployment result to Demand Planning.  The problem is system is sending results on the basis of the recept date.  I want to send the same on the Start Date at the plant.  Is it Possible.  Example is given below

Transit time from Plant to Warehouse is 7 Days, Plant despatch material on 1st (Start Date) and Warehouse is Recing on 7th(Availabilit)   

if i copy the deployment result it copies on 7th that is the availability.  I want the result should be copied to 1st Start Date instead of 7th to the warehouse.

Urgent help is hightly appreciated.

Thanx  in advance

AJ

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

The best would you download the data into APO BW using SNP aggregates.

While loading the data into APO BW, you can manipulate the dates and save the results according to start data.  From APO BW, you can load the data in the respective buckets according to your requirements.

Thanks

Amol