Hello Team,
We have a requirement that Budget/Actual Report S_ALR_87013558 should have value in Object currency.
We have used report painter to get values in object currency, but all values are coming other then remaining order plan value,which is coming as zero.
Checked SAP forums/threads on this,so many discussions are there but not able to get exact solution on this.
Please help me in this regard.
Thanks in advance.
Karan Varshney
Hi Karan,
could you please check is wbs which have remaining order plan is TECO because once project object is TECO commitment and Remaining order plan would be fulfill.
Regards,
Sanjeev