"Assigned" value exceeds "Distributable Budget"

Former Member
0 Kudos

Hi all, in AVAC analysis assigned value exceeds distributable budget.

Distributable: 24000 USD 

Assigned: 25914,59 USD

Tolerance limits:

++/ 3 /100,00                 0,00

Why does this situation occur?

Accepted Solutions (0)

Answers (2)

Answers (2)

kenmelching
Active Contributor
0 Kudos

This can occur when the actuals costs from Purchase Orders post above what was on the PO.   If a PO has a value of 10,000 but the invoice posts for 11,000 the budget is not rechecked when the invoice posts.

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Ken,

That sounds like a bug, is there any OSS note to discuss this behavior as official acknowledgement from SAP?

Thank you,

Paulo

kenmelching
Active Contributor
0 Kudos

I believe the logic is that you've already entered into a contract with the budget approved PO and blocking the invoice would be a contract violation.  I have seen this discussed several times here in SCN.

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Claudio,

Can it be the case that some postings were made when no active AVAC status was in place, or the customizing changes were done during the WBS lifecycle?

I think you can take the status change documents, as well as have a closer look to explode into line items and see at what point the budget was exceeded.

Regards,

Paulo