plan order is not getting updated is process order although created through conversion indicator in APO.

ramesh_kumar78
Explorer
0 Kudos

Hello Experts,

I am getting one issue.Users are converting Plan order into process order in APO through conversion indicator.Now when we are checking this process order in ECC COR3 transaction,the plan order number in assignment field is blank,while in administration tab it is showing as created by APO.

Do have any idead,how plan order is not getting updated is process order although created through conversion indicator in APO.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Is the planned order that it is based on existed in R/3 before the conversion?

If planned orders from APO are not published at all or if a planned order in APO was immediately selected during creation as to be converted, no planned order number is entered in the resulting R/3 manufacturing order.

Also refer OSS note 1723358 - Planned order qty is zero in process order.

Best Regards,

R.Brahmankar

Answers (0)