Dears,
Kindly I have a question concerning my customer requirements , my customer requested to have an enhancement "Z SCREEN" which hits 2 projects doing the following :
1-goods issue for materials on the first project on the first company code
2-Activity confirmation for ps activities on the second project on the second company code
is it applicable and recommended to hit 2 company codes in one screen or should we do an upload program to upload all these data instead
Regards,
Allaa Waked
Standard PS handles multiple company codes within the same project. The only restriction is that all of the organizational objects exist in the same Controlling Area.
Normal transactions for issuing material and confirming activities could be used.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.