Dear Experts
Seeking your kind advice to resolve as follows problem of mine.
Service PO/WO value shows in report S_ALR_87013558 as commitment. And then when I run line item report (CJI5) that service PO/WO value not found, but raw materials commitment value found accurately.
Please see my problem from the as follows screenshot
Budget Report:
Line Item Report
Thank you
Rasel
SAP PS USER
Dhaka, Bangladesh
Hi Rasel,
It might be due to dates selection in CJI5, please check the commitment date.
Regards,
Paulo