Hi Gurus,

I have a sales order for which GATP is getting triggered. Since the corresponding CVC's were not created earlier, i created the corresponding CVC. Later i updated the product allocation in the planning book for the particular selection. what are the other things i should be doing? Is there any program that should be run to update the product allocation in the planning area? Kindly advise.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Sandeep,

Depends on your setup.  Normally,

1. create CVCs

2. Maintain allocation qtys against cvcs in your planning book   

3. copy cvcs to product allocation group

4. copy allocation qtys to product allocation group.

Details of how to do this can be found in help.sap.com

Product Allocations Settings - Product Allocation - SAP Library

Best Regards,

DB49

sandeep_sivaraman
Participant
0 Kudos

Thanks Dogboy 49 for the help.. Followed the steps you had suggested and the SAP help link that you provided helped a lot. You are doing a great job!