Hi Experts,
The STO is returned to the source location , because of some reason.
It appears as Requirement (-ve quantity) in MD04 . And also it is considered as requirement in SCM(EG. appears in RRP3).
Any way ? it can be excluded from requirements in SCM planning. Because CTM considers it for planning.
Or it needs to be controlled in ECC only?
Regards
Abhijit
Hi,
As far as requirement is generated in ECC, it will be transferred to APO as requirement.
So you'll need to stop requirement generation for return orders in ECC.
To achieve this, please refer to note 1919958.
BR, Ada