on 01-03-2016 2:58 AM
Dear GTS Experts,
After checking in Google and SCN I Am posting my question here .
I am new to GTS, presently I have to upload BOM to GTS with preference process.
But I am confused to understand the Settings for BOM-Preference
Could you please explain me the steps involved here..
In my case Vendor declaration also will be included as sub items are from different countries
Please give me guidance how to configure
I have found one link but it tells development also required.
http://help.sap.com/saphelp_gts101/helpdata/en/4c/7a2f409bc971d0e10000000a15822b/frameset.htm
Hi Venu,
I am not certain about your question but below is the process you need to follow.
You need to transfer the BOM's from ECC to GTS.
Once the BOM is available in GTS then you can run the preference determination process depending upon the necessary agreement.
Depending on the procurement indicator you might need to do the Request LTVD.
Once LTVD request is done you can run the preference determination, which will set the preference indicator for the product and you can view that in the product master or preference report.
However, I listed down only couple of steps.
Please do elaborate your requirement so that i can better help you. Thanks.
Regards
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.