on 12-30-2015 11:26 AM
Hi,
Has anyone come across a method of bringing back the % values from phase in / out profiles, using a macro?
I have used macro function 'PRODUCT_PHOUT_END' to determine when a phase out reaches its end date, however I would now like to determine if it is possible to work out the relevant % values.
Example:
Period | Value |
---|---|
W 02.2016 | 95.00 |
W 03.2016 | 75.00 |
W 04.2016 | 50.00 |
W 05.2016 | 25.00 |
W 06.2016 | 5.00 |
Attached is the screen print of the phase out screen which I am referring to.
Any thoughts on this would be much appreciated
Hello,
I think the macro function PRODUCT_PHOUT_END you mentioned is to get the date that is set in /SAPAPO/MSDP_FCST1 -> Assignment, instead of the end date in the attached screenshot which is the time series setting.
Sorry but I don't think there's a macro function that could get/set the % data in time series settings.
You can consider using FM /SAPAPO/FCST_PHINOUT_TSID_SAVE in a BADI macro.
Best Regards,
Ada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.