cancel
Showing results for 
Search instead for 
Did you mean: 

Copy Project with User Status

Former Member
0 Kudos

Dears,

Kindly I need to  know if their is any option to copy a WBS with activities from a project to a new project with their user status

Regards,

Allaa Waked

Accepted Solutions (0)

Answers (1)

Answers (1)

DaveS4
Contributor
0 Kudos

Short answer is NO. When you copy a project it gets initial user status in its status profile.

Former Member
0 Kudos

Dear Dave,

Many thanks for your reply , is there any user exits or Bapi or enhancements to copy user status

Regards ,

Allaa Waked

DaveS4
Contributor
0 Kudos

Allaa,

Please check the below link:

BADI or USER EXITS for Tcode CJ20N!!!! | SCN

If helpful, please close the thread.

Regards,

Dave

sanjeevc
Active Contributor
0 Kudos

Hi Allaa,

Any of structure report can fulfill your requirement so execute CNS41 report here you can get project wbs and network even activity so export data after execute the report.

Regards,

Sanjeev

Former Member
0 Kudos

Dear Sanjeev,

Kindly note that I need to copy the user status , so do you mean to export data and upload it for a new project ?

Regard

allaa

sanjeevc
Active Contributor
0 Kudos

Hello,

yes.... otherwise what is the sense of copy user status for all project objects. even I propose how to copy status of project object.

Regards,

Sanjeev