Risk analysis finished with error. Check log for details.

Former Member
0 Kudos


Hi All,

Merry Christmas in advance!

We are GRC10.0 and SP13

We are facing below issue

Role owner getting the below error while trying run risk analysis and approve grc request

Risk analysis finished with error. Check log for details.

SLG1 shows the below

Correctly define the scenario handler class in CCITS

Also we are unable to approve GRC requests at admin stage as getting into MSMP error.

kindly advise.

Thanks as always!

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

Hi Somik,

Please check the below thread:

Error in Program for Authorization data Synchro... | SCN

It talks about the same error, though highlighted at a different stage

Are you able to run sync jobs successfully?

Thanks,

Priyanka

Former Member
0 Kudos

Hi,

What type of connector do you have?

SAP? WS? LDAP?

It should be defined here SPRO->Governance, Risk and Compliance->Common Component Settings->Integration Framework->Maintain Connection Settings.

Then you should  link all the integration scenarios linked to ypur connector. This link can be established under transaction SPRO => Governance, Risk  & Compliance => Common Component Settings => Maintain Connection Settings (note 1562760 - AC10.0 - Integration Scenarios to Connector link)

surya_appala
Active Participant
0 Kudos

Hi Bose,

Please check if the Integration Scenarios are properly activated.

Regards,

Surya

Former Member
0 Kudos

They are activated