on 12-18-2015 2:31 PM
All,
In which tables can I find the cost component split of materials when I have run the actual costing in Material ledger till the phase of multilevel-price determination.
Best regards,
Wouter
Hi,
Please check the following tables:
CKMLKEPH - Material Ledger: Cost Component Split (Elements)
CKMLKEV- Material Ledger: Cost Component Split (Control Record)
CKMLKEKO - Material Ledger: Cost Component Split (Header)
Regards,
Pavan Kumar Arvapally
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pavan,
the tables that you are mentioning don't reconcile with the periodic unit price after the single and multilevel price determination. I have checked this for a material that I have produced. Keep in mind that I dindn't settle yet the actual costing, since I want to run it on a weekly basis.
Material ledger is active on batch level, however the logic should remain the same.