How to move final forecast data for plant A to Plant B

0 Kudos

Hi,

The final forecast data is available on plant A due to wrong CVCs (Plant A with wrong Sales Org). Now I have to move that data to correct plant i.e. Plant B.

Please let me know all possible solutions.

Thanks in advance.

Regards,

Arpit

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Arpit

You can use standard APO DP realignment process to transfer the FCST from one CVC to other.

Please find below the link which will explain the process step by step.

Please let us know if this information help you.

Thanks

Amol

0 Kudos

Hi Amol,

Thanks for your reply.

It will be helpful if you provide an example to maintain the realignment table and to execute of the realignment run.

Thanks in advance!

Regards,

Arpit

alok_jaiswal
Contributor
0 Kudos

Hi Arpit,

Initially you need to maintain the realignment table - It will based on your MPOS. For example below screen shows that a table defined where data would be copied from Product FG01 to FG02 based on given set of characteristics. After you have defined the setup you can also select the key figure for which you want to copy the data from source to target.

After you have defined the steps - you can execute and then see the result in planning book.

Hope it helps.

Regards,

Alok

Former Member
0 Kudos

Hi Arpit

Please go to T-code /SAPAPO/RLGCOPY - Data Realignment

You can select your PLOB and click on Create/Change Table which will provide you template of your CVC. You can maintain From CVC values vs To-BE CVC.

I would prefer you play around on development system to understand it better.

Please check following link which will give you more information about it.

APO Realignment - YouTube