on 04-23-2007 2:22 AM
hi guys:
I got a trouble about WBS project stock , I created some project stock by T-CODE mb1c 521 Q.Then I created a sales order to sales these stock.But the order can not find the project stock, the project stock's material has been adopted usability check.Now I find the usability check configure , but there is no item about the project stock , only Consignment stock , Standard stock and so on.
Please tell me how can I figure it out.
wishes.
keen
Hi Keen,
Please try using t-code MBBS.