Hello Everyone,
Normally we run mrp manually with "/n/afs/md02" t-code.
2 days ago we tried to use "J_3AM_DISPOSITION" bapi instead of the t-code "/n/afs/md02". Planned orders are created but purchase requisition are not created after the bapi run.
Is there any trick to use this bapi? I try to use same settings for "J_3AM_DISPOSITION" bapi and I am nor familiar with this bapi.
Anyone guide me to resolve my problem?
Thanks in advance...
Hakan Mutlu
12-15-2015 8:31 AM
I found the solution. There is no need to response.
The bapi "J_3AM_DISPOSITION" should run only for afs materials. The bapi which we use for non-afs materials is "BAPI_MATERIAL_PLANNING". After both bapi planned orders and purchase requisitions are created.