Milestone Actual Dates

former_member230675
Active Contributor
0 Kudos

Dear Experts,

Please note that actual dates are not copied automatically to milestone even though I maintained the confirmation parameters.

Any idea what could be the reason?

Thanks

Abdul

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member230675
Active Contributor
0 Kudos

issue solved.

sap suggested to specify Actual start and Actual Finish date in the activity confirmation.

Former Member
0 Kudos

Hi Abdul

Please put POC in milestone details which need to correspond to degree of confirmation in activity.

This should work to bring actual dates in M.S from activity.

Regards

Raman Taneja

sunil_yadav2
Active Contributor
0 Kudos

Hi Abdul,

it depends upon degree of processing while activity confirmation. you can use 100% or final confirmation tick.

try this if this helps you.

thanks

Sunil

former_member230675
Active Contributor
0 Kudos


Hi Sunil,

I already tested that, but still the same.

thanks

abdul

kenmelching
Active Contributor
0 Kudos

Send a screen shot of the actual confirmation.

former_member230675
Active Contributor
0 Kudos

Actual confirmation attached

kenmelching
Active Contributor
0 Kudos

You didn't specify an Actual Date in the confirmation.  Repost the confirmation and enter an Actual Date and see if that corrects it.

former_member230675
Active Contributor
0 Kudos

I tried exactly same way as I did in IDES and it is working perfect. I have done the same config, but not happening in DEV and QAS system.