on 12-10-2015 8:47 AM
issue solved.
sap suggested to specify Actual start and Actual Finish date in the activity confirmation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abdul,
it depends upon degree of processing while activity confirmation. you can use 100% or final confirmation tick.