on 12-09-2015 2:49 PM
Hello,
I had configured the DIP profile to get the 'Material costs' and 'Labor costs'. I was able to see the Labor costs in DP91. However, the Material costs are not flowing over in DP91. Can someone please tell me if I am missing anything? Also, while maintaining the set for 'Materials', how can I do it if the Materials have special characters (Material # A123456-1 or A1234-1). Please see the attached config screens.
Thanks.
Hi Vijay,
use one of two options for material determination, either material or activity type.
try this.
also check consistency using ODP2.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You do not have to use all of the characteristics in the material determination.
Is NO-ACTIVITY-TYPE an empty set? What is your source in the DIP profile, Line items?
Taking out the Activity Type characteristic might help, but if it is an empty set you need to verify that Activity type is blank on the cost line item.
Have you verified that you do have material costs posted to the WBS by looking in COEP? What type of stock are you using on the Project, Valuated or Non-Valuated?