on 12-09-2015 5:55 AM
Hi Friends,
One finding in CO09 stumped me recently. As the CO09 screenshot showing, here a SO and a DO were confimed by 20 qty and 20 qty, but upper "Total display", the "Issues" and "Confirmed Issues" both blank, as I undersand, these two fields should summarize the quantities which listed below.
Then I review the scope of ATP check , the SO and DO requirements are included. And I also checked the SO schedule line category CP, ATP and TOR indicator both marked.
Then it stumped me. Please kindly advise. Many thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Layla,
Could you plz send the screen shot of "Scop of check"
Thanks,
Prashant Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.