Dear PS experts,
I have an issue while making project scheduling i have a project as below:
WBS 1 ---------------
Act 1 -------
ACT 2--------
WBS2-----------------
ACT 3--------
ACT4 --------
all the activities is FS relationship
when i trying to change the relationship between act 2 and act 3 to be SS
scheduling conflict happened as the dates of ACt 3 , 4 and WBS 2 doesn't changed .
my scheduling method : WBS determine dates so the dates of the WBS should be cleared manually and after that making scheduling
I have attach a file of my scheduling configuration.
and i am asking if anyone have automatic solution for this issue ???
Hi Ahmed,
Your schedulign configuration is incorrect. As well as I see you have "WBS determines dates" exist. However you need to determine dates by the network. In the project profile, make sure you make "Strict Bottom-up Planning" . Then once you re-schedule all WBS dates will align to network dates. This is the best practice.
regards,
Dave
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ahmed,
1) OPSA: Proj profile, tab "Planning Board/Dates"
a) Scheduling scenario:1, Wbs scheduling profile : Today Scheduling Fwd.
b) Check "with activities"
c) Planning method: 4 - Strict bottom up to both
d) Calculating with act: 1 - taking activity dates into consideration
Check these settings please. Therefore you should not enter any dates to the WBS elements. By these settings all dates wil be populated by the network dates.
regards,
Dave