Hello Guru,

Please I need a direction.

My client is asking to maintain responsible person and Applicant number in CJ20N (Project builder) per the screen below.

1. For person responsible, I went to transaction code OPS6.

2. Where do I maintain the applicant number on the below screen?

Regards,

FJohn

Accepted Solutions (1)

Accepted Solutions (1)

Paulo_Vitoriano
Active Contributor

Hi John,

It is OPS7.

Regards,

Paulo

former_member564981
Participant
0 Kudos

Thank you Paulo for the quick response, appreciated.

Ticket closed.

Regards,

FJohn