Dear Experts,

I have a requirement were we create a demend in APO for 1 finished SKU and transferd to ECC, Weather this can be slit in to 2 SKU's

in ECC and we the BOM structures all ready available in ECC.

My Question is weather the above requirement is possible, how?  or please suggest any other alternative way for doing it.

Thanks in advance.

Warm Regards

Ashwin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

I hope you are talking about FCST release from DP --> ECC i.e. /SAPAPO/REL_TO_OLTP - Release from InfoProvider to ERP System. For this you require to get the Demand planning FCST into APO BW cube. You can surely perform the splits within APO transformations while loading the data from planning area -->APO BW. You require to build the logic how you can split the FCST and link between 2 SKUs.

You could build this relation in T-code /SAPAPO/MC7B - Product Split . You can ask your BW consultant to use this information and split the FCST while loading into APO BW info provider from where you are planning to release it to ECC system.

Request you to please cross check from your side and let us know if this information helps you.

Thanks