Hello,
We are facing issue, Commitment is not posting to WBS while creating PR/PO from PS and MM both module. But if we create Service PR/PO all postings of Commitment done as per standards.
I have Checked the PS config, OBYC settings and G/L Settings, all are fine and unchanged. Only thing what we did is config for MRP. Later MRP as requirement changed we reversed all config done for MRP.
Does MRP settings are the base for this issue? I am not sure where did i went wrong, Please Help me.
Regards,
Omkar Deshpande
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Omkar,
Please let us know which account assignment category is used by you.
if you are using network activity (N) than their could be reason of control key. control key does not activated for cost.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Omkar,
Please check OKKP if configured correctly than this might be issue of GL/cost element.
please check with FI person.
also check below link:
PR created but not showing in CJI5 | SCN
thanks
Sunil
Just check once the PR/PO is created with correct account assignment category using WBS code. As per standard PR/PO should be shown under committments of WBS.
Regards
Bhaskar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.