Hello,

We are facing issue, Commitment is not posting to WBS while creating PR/PO from PS and MM both module. But if we create Service PR/PO all postings of Commitment done as per standards.

I have Checked the PS config, OBYC settings and G/L Settings, all are fine and unchanged. Only thing what we did is config for MRP. Later MRP as requirement changed we reversed all config done for MRP.

Does MRP settings are the base for this issue? I am not sure where did i went wrong, Please Help me.

Regards,

Omkar Deshpande

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear All,

Thanks for helping me for the same.... Issue was generated because of G/L. Inventory Account (Balance sheet G/L) should be Cost element to view all reports in SAP PS.

Check the following link for Better understanding.

Regards,

Omkar

Answers (2)

Answers (2)

sunil_yadav2
Active Contributor
0 Kudos

Hi Omkar,

Please let us know which account assignment category is used by you.

if you are using network activity (N) than their could be reason of control key. control key does not activated for cost.

thanks

Sunil

Former Member
0 Kudos

Hi Sunil,

We are using Account Assignment Category as (P) Project

Please Find Below the screenshot

And also about the Control Key all are activated for Cost. I have checked and Confirmed.

Regards,

Omkar

sunil_yadav2
Active Contributor
0 Kudos

Hi Omkar,

Please check OKKP if configured correctly than this might be issue of GL/cost element.

please check with FI person.

also check below link:

PR created but not showing in CJI5 | SCN

thanks

Sunil

Former Member
0 Kudos

Hi Sunil,

OKKP settings are fine and as per standards. No changes on standard. Kindly see below

Regards,

Omkar

bhaskar_basam
Contributor
0 Kudos

Just check once the PR/PO is created with correct account assignment category using WBS code. As per standard PR/PO should be shown under committments of WBS.

Regards

Bhaskar

Former Member
0 Kudos

Hi Bhaskar,

Yes PR/PO is created with proper Account Assignment Category using proper WBS.

Regards,