on 12-05-2015 9:19 AM
Hi Folks,
I have one doubt when I was doing easy cost planning in Internal process,
1. I have selected Catagories E and Sources is :- 1000 and Plant is 1000
2. Given Quantity 10, and press enter then automatically system will calculate amount is 3000/-
Here I need to know, how system calculate amount? , Means where the system is pick the price?
In that plan I didn't give any cost center, But system cost plan has triggered to cost center.
Please give valuable suggestions.
Thanks
Venkat
Hi Pratap Bhat,
Thank you very Much for given valuable information.
I will check and confirm you
Thanks
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Venkat,
Could you please specify what is the "Source" that you have mentioned above? Normally for category E, you will have to input the cost center and the activity type. So if in activity type price planning (KP26) there is already a defined value of 3000 for a combination of cost center 1000 and activity type 1000, then the system will pick this price.
-Pratap
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.