MAT time confirmation

Former Member
0 Kudos

Dear Experts

How the availabilty of material time is calculated in Block Planning .As i am getting availabilty date as end of block + Gr  it is ok .

But availabilty time I am getting as 4 hours difference after end block

Example my block ends on 03/12/2015 23:00 then MAT is 13/12/2015 03:00

How these time is calculated ??

Regards

jaisree

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Expert

Any help on above question .Your help will be appreciated .

Regards

Jaisree

Former Member
0 Kudos

Hi Jaisree

I am not the expert in the block planning but I think following links will provide you more details of block planning. I think you can refer them with your scenario and see if everything is configured correctly with in your system.

Scenario - Block Planning with PDS - Supply Chain Management (SCM) - SCN Wiki

Carrying Out Block Planning - Functions for Block Planning - SAP Library

Thanks

Amol

Former Member
0 Kudos

Hi Amol

I have gone through all links but i was not able get my answer in above link .

Regards

Jaisree

Former Member
0 Kudos

Hi,

I think this is OK, as the block is set on the Resource and nothing to do with GR of material . THe GR is calcualted separately considering the Handling resource.

Regads,

Anil

Former Member
0 Kudos

Hi Jaisree

check your material master GR time in  the  product master

regards

Virender

Former Member
0 Kudos

Hi Anil /Virender

Actually i want to know the time not date .pls refer my question

Regards

Jaisree