on 12-03-2015 6:40 AM
Hi,
We have batch managed materials with characteristics value. Whenever i am receiving a material through MIGO, i am updating the characteristics ( For eg Viscosity : 20 ) for which a batch number is getting created automatically.
When i am doing a second GR with a different characteristics value ( Viscosity : 80 ) a new batch is getting created.
At this outset, we need a functionality wherein a third GR received with Viscosity : 20 should not create a new batch. The system should prompt us a message the characteristics value already entered had a batch already posted in to your system. Do you still need to create a new batch ?
Do we have any configurations to achieve this functionality. Please expedite.
Regards,
Dilli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.