Hello,

Need to know if we can transport few selected newly created connectors or can we create directly in the individual GRC systems.

Not sure what SAP recommends and how it is dealt with.

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Dear Mukesh,

It is not possible to transport connectors, please create the individual connectors in the systems,

Regards,

Rafael

Former Member
0 Kudos

Dear Rafael,

Thank you for your inputs.

I want to make that box for SOD check.

What should be the order of jobs setup for the first time for new connectors.

is this correct order or i'm missing something ?

A -GRAC_REPOSITORY_OBJECT_SYNC

B- GRAC_PFCG_AUTHORIZATION_SYNC

C- GRAC_BATCH_RISK_ANALYSIS


Thanks,

Mukesh

0 Kudos

Hi Mukesh,

You can do in this order, but do not forget to schedule all the jobs, please see link below for more information, The Repository - GRC Access Control 10.0 - Governance, Risk and Compliance - SCN Wiki

Regards,

Rafael Guimbala

Answers (1)

Answers (1)

0 Kudos

Create connectors in each system, for example in the development system you may need development connectors whereas in QA you many need to QA connectors.