We are planning to use the add-on SCMAPO to ERP

We are running SAP ERP version 2005 (enhancement package 7.40) on HANA

Will this add-on give us gATP ?

Is there a licence cost for this add-on ?

We are also planning to look into the STO process....

Can you link me to information regarding the gATP and STO process ?

Today we are running StockTransportOrderDelivery (UD)

And a last question....

Is it possible to run gATP in a project-network (transaction CJ20N) ?

Please advice

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi Erik, The way newly implemented PPM solution is designed / configured it solves only one purpose of customer order schedule from SAP PPM to SAP PS and further to SAP PP by applying constraint dates. However it is not able to feed back the delays from SAP PP and externally procured items to SAP PS and PPM. We are trying to suggest them IBP but is there any project where Bristlecone has implemented IBP +SAP PS

former_member184443
Participant
0 Kudos

Gurus

Today we are running normal ATP in a project network (transaction CJ20N)


gATP - rule based - is it also possble to run this in a network ?


Please advice