on 11-30-2015 1:22 PM
Hi All,
Please suguest the setting/Config in ECC :so that In APO to create Planned orders for Primary resource/workcenter first after that when Overload Primary resource shift /create planned orders to Secondary Resource
1) Repetitive Routing CA23 using in current project which has different version with different Resource/work center in PDS which is not working
In Routing have different production versions with different group with different Work center: which is not working for creating planned orders for primary resource first then if overload shift to secondary resource ,So I tried to test for Normal Routing
2) Normal Routing CA02: I Tried do configuration and did testing for Normal Routing but not working please suggest
I have tried to do in 3 different process in Routing 1)2 Operation with diiferant workcenter 2)Sequence in routing 3)Created Characteristics and class and assign to routing but getting error
Regards
Vijaya
Hello,
Could you tell if the secondary resource is created on Alternative sequence or Parallel sequence in routing?
Regards
Ashutosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thanks for response,
created Alternatice sequence in CA01 and in Alternative sequence created/assign secound workcenter,Please find the screen shots below
Please suggest the setting in ECC and APO to achieve the reqiurement:Use the primary resource first then secundary resource of specific product while running ppds run or Resheduling run
Hello,
In the standard system, you cannot display alternative routing sequences in a PP/DS runtime object
generated in R/3.You can use the BADI implementation of the CUSLNTRTO_ADDIN BAdI described in this note to display alternative routing sequences in alternative modes.
If the R/3 routing contains a parallel sequence, the transfer to APO has operations appearing in the source of supply in SAP APO (PPM, PDS) that are from the parallel sequence, in addition to the operations triggered by the master sequence operations. The parallelism is mapped using relationships.
please refer SAP note 507025 - Examples of customer enhancements/437400 - Alternative and parallel sequences in APO integration.
Regards
Ashutosh
Hello,
This Badi is to be used in ECC while CIF transfer.
BADI Name: CUSLNTRTO_ADDIN
Method: CHANGE_CIF_STRUCTURES /CHANGE_EWB_STRUCTURES
Please work with your Technical team to implement this BADI and method in accordance to your requirement.
I believe you are using PDS and not PPM
You can Refer following SAP notes.
507025 - Examples of customer enhancements.
217210 - Mapping of alternative sequences in APO System for this
357178 - Examples for customer enhancements in run-time object
Regards
Ashutosh
what about the characteristic and class maintained in ECC,not require right ? even alternative sequence will achieve the requirement of Using primary resource the secondary resource
Currently we are using PPDS Huristics Planning of Standard Lots "SAP_PP_002" is it ok right this huristics will work for creating Planned order in primary resource then secondary if implement notes or Badi
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.